BPMN - Intermediate events docking to the activity borders

Hi,

In the past I couldn’t attach intermediate events to the border of an activity.

Now, the intermediate events that I need to be stand alone on a ad-hoc subprocess activity are docking to the border against my will.

Is there a way to un-dock the intermediate events from the activity border?

49%20PM

Hi Filipe,

Did you try to drag a little further to pull the intermediate event away from the sub-process? If that doesn’t work, can you send us a sample project that could repeat the problem? Or maybe you could describe the steps about how to repeat the problem from scratch.

Thanks,

Antony.